Blank recording aid • version 4 November 2026 • derived from the Gridinta onshore inspection checklist. For competent personnel working to an agreed scope and approved procedures. This is not a work instruction, certificate, acceptance criterion or release-to-service authority.
Before recording findings: confirm the project safety and access gate separately. Choose the method and extent from the agreed scope. State “not inspected”, “inaccessible” or “not applicable” with a reason where needed; a blank cell never means “passed”. No severity scale is supplied: record the project’s authorised basis or mark severity pending review.
1 rotor/hub/pitch • 2 nacelle/yaw/auxiliaries • 3 drivetrain • 4 tower/foundation/site • 5 electrical/controls/LPS. Systems overlap; identify the physical location as well as the group. Repeat this worksheet or add a referenced report for additional defects.
| Component / item | Method / procedure ref | Coverage achieved / limits | Finding / severity basis | Evidence / photo ref | Follow-up / owner / due date |
|---|---|---|---|---|---|
| Blade surfaces and previous repairs Blade ID, span/chord location, viewing method and extent | |||||
| Lightning receptors / blade bonding Visible coverage and test-report reference if in agreed scope | |||||
| Hub, pitch bearings and drives Interfaces, feedback, lubrication and visible coverage | |||||
| Additional item / location |
Preserve original evidence separately. Image / sample references must resolve to the project record. Do not infer a healthy hidden area from a normal result elsewhere.
| Component / item | Method / procedure ref | Coverage achieved / limits | Finding / severity basis | Evidence / photo ref | Follow-up / owner / due date |
|---|---|---|---|---|---|
| Enclosure, drains, bedplate and frame Ingress, corrosion and structural interfaces covered | |||||
| Yaw bearing, drives, brakes and cabling Agreed inspection scope and accessible coverage | |||||
| Cooling, hydraulic and safety/access equipment System boundaries; specialist statutory reports remain separate | |||||
| Additional item / location |
Preserve original evidence separately. Image / sample references must resolve to the project record. Do not infer a healthy hidden area from a normal result elsewhere.
| Component / item | Method / procedure ref | Coverage achieved / limits | Finding / severity basis | Evidence / photo ref | Follow-up / owner / due date |
|---|---|---|---|---|---|
| Main bearing, shaft, couplings and brake Component identity and accessible coverage | |||||
| Gearbox lubrication, filters and oil history Sample ID/date, operating context and laboratory report | |||||
| Gearbox internal surfaces if scoped Entry point, component location, image references and unseen areas | |||||
| Generator and associated systems Configuration, cooling and agreed specialist checks | |||||
| Additional item / location |
Preserve original evidence separately. Image / sample references must resolve to the project record. Do not infer a healthy hidden area from a normal result elsewhere.
| Component / item | Method / procedure ref | Coverage achieved / limits | Finding / severity basis | Evidence / photo ref | Follow-up / owner / due date |
|---|---|---|---|---|---|
| Tower shell, welds, flanges and coating Elevation/orientation and extent; specialist NDT reference if scoped | |||||
| Bolted joints and foundation anchors Joint ID, applicable procedure and measurement report | |||||
| Foundation, drainage and site access Located observations, concrete/interface and access coverage | |||||
| Additional item / location |
Preserve original evidence separately. Image / sample references must resolve to the project record. Do not infer a healthy hidden area from a normal result elsewhere.
| Component / item | Method / procedure ref | Coverage achieved / limits | Finding / severity basis | Evidence / photo ref | Follow-up / owner / due date |
|---|---|---|---|---|---|
| Cabinets, cabling, earthing and bonding Equipment identity and agreed qualified assessment | |||||
| Converter, transformer and protection interfaces Boundary of inspection and specialist report reference | |||||
| Controls, safety functions and LPS tests if scoped Approved test-plan reference and actual coverage | |||||
| Additional item / location |
Preserve original evidence separately. Image / sample references must resolve to the project record. Do not infer a healthy hidden area from a normal result elsewhere.
Uninspected areas / missing data / reasons / required repeat access
Urgent findings escalated to whom and when / reference to separate operating decision
Outstanding action register / responsible person / decision date
Attached reports / photographs / samples / calibration / data extracts
Owner review / acceptance of report / next inspection scope